gantt
title Rotorua Lake Modelling – PC10 Deliverables
dateFormat YYYY-MM-DD
axisFormat %b %Y
section Catchment Pilot
SWAT-MODFLOW pilot (3 catchments) :a1, 2025-11-26, 90d
section Lake Model Upgrade
CMIP6 Data Processing :b1, 2025-11-07, 30d
GLM-AED model upgrade :b2, 2025-11-24, 50d
GLM-AED model calibration :b3, 2025-12-08, 50d
section Scenario Testing
Initial climate scenarios :c1, 2026-01-01, 30d
Preliminary advice re Rotoiti :c2, 2026-03-01, 45d
GANTT Chart
Below is the GANTT chart outlining the key deliverables and timeline for the Rotorua Lake Modelling – PC10 project: